Price monitoring request No. 1140368 
Execution of design works on the object "construction of wind turbine 660 MW and the Wu plant. Kochubeyevskaya VPP"

Execution of design works on the object "construction of wind turbine 660 MW and the Wu plant. Kochubeyevskaya VPP"

Purchasing items:
1. execution of project works on the object "construction of wind turbine 660 MW and the Wu plant. Kochubeyevskaya VPP» (1 ЕР)
Publication date:
Bids submission deadline
Bids can also be submitted after the expiry of the specified period. However, bidding organizer has the right not to consider the bids submitted after bids submission deadline.
:
10.12.2018 23:59
Last edited:29.11.2018 19:52
Responsible person:Titov Igor' Vladimirovich
Organizer (Initiator):AO "VETROOGK"
Additional info
Payment terms:the customer will pay to the contractor an advance payment of 30 (thirty)% of the contract price within 30 days from the date the contractor provided the original account and to ensure the return of the advance payment and ensure the fulfillment of the contractor's obligations under Contract, except for the guarantee obligations (provision of the contract). Payment of advance payment before the provision of collateral is not carried out, and the customer is not responsible for the violation of terms of payment.
Payment of the contractor's work is carried out upon completion of the contractor's execution and acceptance by the customer of all work (stages 1-3) under the agreement. The customer pays for the completed works within 30 (thirty) calendar days after the parties signed the Act of acceptance of the executed works and provided the contractor with payment documents (invoice, invoice for payment), prepared on the basis of Estimated documentation, provided that the customer is transferred to the full extent of the work results, corresponding to the 4.1.1 of the technical specifications, issued in accordance with the requirements of paragraph 8.2.1 of the technical specification, as well as the provision of enforcement Guarantee obligations of the contractor.
If the customer has agreed in writing the interim acceptance of the individual stages of work (Stage 1, Stage 2, Stage 3) the payment of works performed by the contractor is carried out upon completion of the contractor and acceptance by the customer of the volume of work Appropriate stage. The customer pays 95% of the cost of the executed works within 30 (thirty) calendar days after the signing of the Act of acceptance of the executed works on the corresponding stage and provision of payment documents by the contractor (invoice, account For payment), prepared on the basis of the estimated documentation, provided that the customer is transferred to the full extent of the results of the phase, corresponding to the 4.1.1 of the technical specifications, designed in accordance with the requirements of 8.2.1 of the technical specification.
Payment of funds in the amount of 5% of the cost of the work performed by the contractor shall be made within 30 (thirty) calendar days after the signing of the act of acceptance of completed works in respect of the last stage (hereinafter-the Final Act of acceptance Provided by the contractor for payment documents (invoice, invoice for payment) and ensuring the performance of the contractor's warranty obligations.
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Documentation provision procedure:Documentation relating to this call for bids is available in e-form free of charge at B2B-Center e-marketplace (www.b2b-center.ru) starting from the date the call for bids is published.
Please note that this Prices Monitoring Request is a procedure aimed at enabling the Organizer to determine the maximum initial contract price for a call for bids to be held afterwards, and imposes no obligations on the Organizer as to entering into a contract.
 
 
 

  Submit a question
Submitted bids
Status: archived.
Total: 1