Not applicable. Proposal shall cover the entire lot.
Hide prices and bidders' names during bids submission period:
Yes
Supplier should not be recorded in the register of mala fide suppliers
The Organizer has set a requirement as to the supplier's not being recorded in the register of mala fide suppliers. Supplier's compliance with this requirement shall be checked by the Organizer on their own.
:
Yes
Participation of small and medium businesses
Organizer has initiated the bidding only for small and medium businesses to participate. Verification of compliance with the criteria for being qualified as small and medium businesses is to be performed by the organizer.
:
Участниками данной закупки могут быть только субъекты малого и среднего предпринимательства
Payment terms:
40% of the value of the goods shall be paid within 30 (thirty) calendar days from the moment of signing the contract, the contracting authority by transferring money to the account of the supplier;
50% of the value of the goods shall be paid within 30 (thirty) calendar days from the date of its delivery to the warehouse of the customer;
10% of the value of the goods shall be paid within 30 (thirty) calendar days from the date of signing of the act performed by commissioning and briefing personnel, but no later than 60 (sixty) calendar days from the date of delivery of the goods.
The value of the goods should be included the cost of packing and marking of the goods, the NDP coaching professionals, as well as delivery to the buyer's warehouse, located at: str., Smolensk. Frunze, 74
Delivery terms:
delivery to the buyer's warehouse, located at:
str., Smolensk. Frunze, 74 is carried out by and at the expense of the supplier. The supplier has the right to attract for the fulfilment of the obligations on delivery of the goods by third parties, in its sole discretion, without further authorization from buyer.
Delivery should be transport made up the registration registered in Russia, on the territory of JSC "Smaz» RUSSIAN citizens only allowed the import of foreign goods is forbidden.
The deadline for delivery of the goods is not more than 200 (two hundred) calendar days from the moment of signing the contract.
The goods must be packed in accordance with the rules of storage and transportation.
After delivery of the equipment to a warehouse of the buyer, the buyer is obliged within 10 (ten) working days to perform the following work:
- moving equipment at the place of installation;
- installation of the equipment for the Foundation and provisional reconciliation;
- power supply, compressed air.
Following the execution of these works the buyer informs the seller written notice of readiness for the conduct of commissioning works (hereinafter referred to as RTD).
Supplier upon receipt of the above notice shall, within 30 (thirty) business days to perform the NDP.
Allowed early delivery and implementation of the NDP.
Venue of bids examination:
214006, Смоленская обл., г. Смоленск, ул. Фрунзе, д. 74
Date and time of bids consideration:
10.05.2018 10:00
Results date and time:
11.05.2018 14:00
Georeferencing:
214006, Смоленская обл., г. Смоленск, ул. Фрунзе, д. 74
Venue of bidding:
This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Procurement documents provision procedure:
Procurement documents in electronic form are available free of charge at B2B-Center marketplace (www.b2b-center.ru) starting from the date of publication of the procurement procedure.
Organizer has decided to cancel the call for bids.
Call for bids cancellation date: 05.06.2018 at 14:59.
Cancellation date: 01.06.2018
call for bids cancellation reason: